Current work on 1057 Bellows Avenue continues to progress well. Roofing workers and the drywall crew are underway. The revised schedule is as follows:
Dec 3 – Drywall will be complete
Dec 5 – trim work to be installed
Dec 6-10 – Prime and paint (we have a team in place)
Dec. 8-10 – Install kitchen cabinets (help is needed)
Dec 10-14 – Install tile (help is needed)
Dec 15-20 – Install carpet (to be contracted)/ /fixtures (help is needed)
Dec 21-24 – Final Inspection
Again, I can’t stress how pleased we have been with the response we have received. I apologize for those who have not been able to plug in, but we are having to adjust things continually because of our time frame. Thanks for being patient.
I also want you to know that we are working on another property that has just come online for us. It is a two bedroom town home that we hope to have ready by December 16th. The scope of this project is not nearly as intense.
David C Gay
Executive Director
Lower Lights Ministries, Inc.
1066 Bellows Avenue - Columbus, Ohio 43223
614.228.3855 (phone) 614.228.1255 (fax)
www.lowerlights.org
Thursday, November 29, 2007
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment