Thursday, November 29, 2007

Lower Lights Construction Update

Current work on 1057 Bellows Avenue continues to progress well. Roofing workers and the drywall crew are underway. The revised schedule is as follows:

Dec 3 – Drywall will be complete

Dec 5 – trim work to be installed

Dec 6-10 – Prime and paint (we have a team in place)

Dec. 8-10 – Install kitchen cabinets (help is needed)

Dec 10-14 – Install tile (help is needed)

Dec 15-20 – Install carpet (to be contracted)/ /fixtures (help is needed)

Dec 21-24 – Final Inspection

Again, I can’t stress how pleased we have been with the response we have received. I apologize for those who have not been able to plug in, but we are having to adjust things continually because of our time frame. Thanks for being patient.

I also want you to know that we are working on another property that has just come online for us. It is a two bedroom town home that we hope to have ready by December 16th. The scope of this project is not nearly as intense.

David C Gay
Executive Director
Lower Lights Ministries, Inc.
1066 Bellows Avenue - Columbus, Ohio 43223
614.228.3855 (phone) 614.228.1255 (fax)

www.lowerlights.org

No comments: