Lower Lights Construction Update

Current work on 1057 Bellows Avenue continues to progress well. Roofing workers and the drywall crew are underway. The revised schedule is as follows:

Dec 3 – Drywall will be complete

Dec 5 – trim work to be installed

Dec 6-10 – Prime and paint (we have a team in place)

Dec. 8-10 – Install kitchen cabinets (help is needed)

Dec 10-14 – Install tile (help is needed)

Dec 15-20 – Install carpet (to be contracted)/ /fixtures (help is needed)

Dec 21-24 – Final Inspection

Again, I can’t stress how pleased we have been with the response we have received. I apologize for those who have not been able to plug in, but we are having to adjust things continually because of our time frame. Thanks for being patient.

I also want you to know that we are working on another property that has just come online for us. It is a two bedroom town home that we hope to have ready by December 16th. The scope of this project is not nearly as intense.